garage/second floor
Work on the garage and the second story.
Garage
Here they are building and pouring the foundations for the garage.
First floor
The trusses are going in the ceiling of first level for the second floor.
8/20/13
The pour was not today… but it will be bright and early tomorrow morning! They had some things that had to be finished and the pumper truck was not available so tomorrow it is!
8/14-19/13
Building the walls before the first floor pour!
floors and walls
Finishing the floor trusses, and putting down the actual floor. (there is more to come with that…) and them more work on the walls.
Floors
Here you can see them putting down the insulating foam and then the white foam that they snap the in floor heat pipe into. They do the in floor heat late into the night and the next day they come to pour half of the floor. The next day they do the other half. All of this took about a week…
Well
Here is a short little video of them working on the well…