Silver Ducts in the rafers

shingles and windows begin.
October is half over and the weather challenges continue. It snows or rains a lot more that I remember for normal years. The shingles are on and the progress should be more visible after next week as the windows and siding are scheduled (weather permitting) for this weekend and next week. Inside, the duct work is progressing for the air conditioning and the plumbing waste system is in but the supply system has stalled due to other commitments by the plumber. He should be back Monday. The electrician is still restoring power to over 2200 of his customers as of yesterday (10/15/13). I’ve added pictures of the shingles and a video time lapse of the snow storm.