Archive | October 2013
October is half over and the weather challenges continue. It snows or rains a lot more that I remember for normal years. The shingles are on and the progress should be more visible after next week as the windows and siding are scheduled (weather permitting) for this weekend and next week. Inside, the duct work is progressing for the air conditioning and the plumbing waste system is in but the supply system has stalled due to other commitments by the plumber. He should be back Monday. The electrician is still restoring power to over 2200 of his customers as of yesterday (10/15/13). I’ve added pictures of the shingles and a video time lapse of the snow storm.
Siding
Here is siding getting put up.
Interior work
They have been busy inside. Plumbing, duct work, and finally getting the doors and windows in!
October progress
Roofing
Most of the underlayment goes on right before the big storm hits. Logan gets some more digging done on the north side of the house.